Rope Access Services

From Cleaning and Maintenance, To Compliance and Installation, BC3 Offers A One Stop Solution For All Your Building and Construction Needs.

Novena Medical Centre

Novena Medical Centre

BC3 Solutions was engaged by CBRE to carry out Anchorage points Pull out tests on 2nd July 2018. The areas / location of works covered is noted below as per contractual basis:
– Roof Top
– Level 8 Swimming Pool areas
– Level 8 Garden areas
– Level 8 Gym and Banquet areas
– Level 6 and Level 4 areas

BC3 Solutions and CBRE have partnered up to provide a breakdown in the tender exercise, which includes the location of works for affected areas and the specific sites’ details to be tested.

BC3 Solutions was provided with the work schedules for work areas to be carried out in conjunction with Workplace Safety and Health. We have completed the site inspection for both buildings and worksites. Pre-work documents were submitted on time, acknowledging the general requirement and workmanship.

BC3 Solutions has completed the work scope as requested by MCST 1673 in fulfilling the contract terms virtually and in a safe timed manner without compromising on the standards and adhering to the client requirements and procedures.

A total of 9 days was spent to completion for the building areas utilizing our group of qualified and experienced rope access technicians.

Below detail, the photos during façade cleaning and inspection works. We have met with the Client requirement, and all involved were informed of our progress from start to end of the cleaning contract.